Roofing & Cladding enquiryFull strip and resheet of this building where the asbestos roof had come to the end of its lifespan. All the asbestos and plasterboard was removed and disposed of, adhering to all safety regulations. A coverworld twin skin built up system was then installed to bring it up to the value. We also transformed the asphalt flat pitched roof into a 6 degree pitched roof with new steelwork.
Area:
Roof and vertical 1,200 m2
Products Used:
Coverworlds twin skin built up system 240 mm on the roof and 180mm on the sides.
Colour:
Gooswing grey
Time to complete:
6 Weeks